38.5 Further
Investigations and Meetings

At the beginning of September 6 Finnish statements of the key witnesses of the crew and the statement taken in Hangö from the nautical student Rain Oolmets were received from the Finnish JAIC. Almost one year after the casualty had passed before the first statements could be studied and evaluated by this 'Group of Experts'!
In the meantime Stenström continued to give interviews in support of the JAIC scenario and cause consideration and, in particular, drew the attention of the media to the poor condition of part of the visor hinges and the locking devices for which, in his view, the building yard was to be blamed with the naïve argument that the JAIC was unable to find anybody who would admit to have done repairs as sloppy as described during the lifetime of the vessel, or that they could not find any recording on them.
Nevertheless the communication between Stenström and this 'Group of Experts' was continued.
At a further meeting in Stockholm on 2 October Stenström reported that the next JAIC meeting would be on 17/18 October in Tallinn. At the subsequent meeting in Stockholm on 5 December, the technical part written by him - see the Part-Report - would be finally agreed upon. The JAIC's scenario and cause considerations would not be changed. Nevertheless, he agreed to have a look at the facts considered by this 'Group of Experts' not to be in dispute and, further, to another meeting to be held in Stockholm during the first week in November. Stenström also reported that the tank tests with a model of the ESTONIA had shown that at a speed of 10 kn the same loads on the visor occurred as at a speed of 14.5 kn, however not as often.
Stenström furthermore admitted that up to 30 ts. water could have been in the visor.
Note: This was not surprising because this is the quantity indicated by the highest water mark visible inside the visor.
This means that the lower part of the bow ramp including the hinges had been under water. Stenström further stated that the heavy damage to the port outer ramp hinge - as visible on the videos - had existed already since some time before the casualty. As a result - in his opinion - the bow ramp could not be closed properly at the port lower edge, thus was open to the visor up to about 20 mm. This - so he said - was also the reason why the port lower securing bolt of the ramp was unable to engage its mating pocket at the ramp side. He then stated that the Estonian crew had put this severe damage repeatedly on the repair list since some time already, however without N&T doing anything. He said that he had copies of these repair lists. Stenström argued further that because the bow ramp had been partly open for some time already, there must have always been water on the car deck if the theory of the German 'Group of Experts' would be correct. However, as there had obviously not always been water on the car deck the visor could not have been filled to the outside water level. Unfortunately the observations of previous passengers and, in particular, the statement of Pilot Bo Söderman - see Enclosure 12.4.4.161 and Subchapter 12.4.4 - were at that time not yet known to this 'Group of Experts'. They prove beyond reasonable doubt that there had indeed been water on the car deck already in 1993 and the worse the weather got the more water had been on the car deck.
In any event, Stenström had stated that the bow ramp could no more be properly closed for some time before the casualty, that the crew had demanded repairs which were rejected by N&T. It follows already from this fact that the ferry had been initially unseaworthy with the knowledge of the technical managers and owners since some time before the casualty already. No mention of this serious deficiency is made in the Final Report with the exception of the following remark on page 42 - Subchapter 3.3.6 - "It was known that the play in the ramp hinges was approaching the point where corrective action would be needed".
By letter of 27 October the "the undisputed facts" were submitted by this 'Group of Experts' to the JAIC and a copy of the letter is attached as Enclosure 38.5.
Note: The letter was registered on 2 November 1995 under B125 in the logbook of the Swedish JAIC and was declared classified until 9 March 1998.
This 'Group of Experts' expressed once again its regret that it was not possible for the JAIC to travel to Hamburg and/or Papenburg:
"Once again we have to express our regret that is has not been possible for you to visit us here in Hamburg and/or in Papenburg. Many things would have been much easier to transfer to you respectively prove to you, if you would have spoken to the individuals personally and asked your own questions, be that now the von Tell representative Todsen, the BV surveyor Lohmann or the welders, locksmiths, foreman, etc. of Meyer Werft having been engaged respectively responsible, e.g. for the welding of bushings into the lugs of the Atlantic lugs or the lugs to A-deck or the steel bushings into the bores of the visor arms etc., all of whom have been identified. Anyway this can still be arranged if you should wish so.""
As there was no response, it was decided to take one of the welders to Stockholm to the next meeting. This was welder Koenen who had welded, among other things, the locking devices in the foreship area of ESTONIA during its construction.
The next meeting with the JAIC took place in Stockholm on 9/10 November and before the meeting this 'Group of Experts', together with the Meyer Werft welder Koenen, had about two hours time to look - undisturbed and in detail - at the recovered objects stored in the basement of the KTH. The comments of welder Koenen after this close inspection of the Atlantic lock lugs can be summarised as follows:

This means that the Atlantic lock found was not the original and this was presented in detail to the JAIC at the meeting commencing at 11.00 hours with welder Koenen also in attendance.

The JAIC was represented by the following persons:

Börje Stenström : for Sweden
Mikael Huss :
Tuomo Karppinen : for Finland
Klaus Rahka :
Prof. Jaan Metsaveer : for Estonia

To begin with the findings and conclusion of the inspection of the Atlantic lock lugs were submitted in detail and in summary. It was concluded that the lugs of the Atlantic lock welded to the forepeak deck were no more original. Due to the red paint below the blue it had to be assumed, however, that the lugs had been exchanged already when the vessel was still "VIKING SALLY" which was noted by the JAIC in silence and without further comments.
Subsequently the participants of the JAIC were invited to ask questions to welder Koenen about the yard practice, welding standards or whatever else, but in particular about their view expressed as in the Part-Report conclusions, namely:
"- The visor locking devices were constructed with less strength than required according to calculations. It is believed that this discrepancy developed due to lack of sufficiently detailed manufacturing and installation instructions for certain parts of the devices." Not a single question was, however, put to welder Koenen who left with the impression that none of the experts of the JAIC was the least interested in his testimony. His impression was correct, because the JAIC reiterated in their Final Report what they had assumed to be the facts already in November 1994.
"The attachments were constructed with less strength than the simplistic calculations required. It is believed that this discrepancy was due to lack of sufficiently detailed manufacturing and installation instructions for certain parts of the devices."

The meeting went on and as this was the last meeting in Sweden and also the last one with Börje Stenström attending, the subjects of discussions shall be outlined in some detail:

JAIC: The vessel was assigned the highest B.V. class symbol, it could consequently operate in worldwide trade.
German 'Group of Experts': This is true, however, the trading area of a passenger vessel is defined in the PSSC, which is issued only after the class certificate has been submitted to F.B.N. The PSSC restricted the trade of the vessel to "kustfaart mellan Finland och Sverige", i.e. coastal trade between Finland and Sweden.
JAIC: This restriction referred to the radio operator only. In case AB Sally would have put a radio operator onboard the ferry could have traded "Short international voyages", i.e. 600 nm between 2 ports and no more than 200 nm from the next port, i.e. the ferry could have sailed between Helsinki and Gothenburg.
German 'Group of Experts': It had been agreed in the building contract that the vessel had to be built for an "intended trade", i.e. for the Viking Line service Turku-Mariehamn-Stockholm.
JAIC: This referred only to the "partial collision door" while the contract is otherwise open.
German 'Group of Experts': The well known fact that the "partial collision door" was not installed is indeed proof that the vessel was built for a particular trade, for which according to the opinion of the responsible maritime administration - F.B.N. - such a "partial collision door" at the location required by SOLAS was not necessary.
JAIC: It was also in 1979/80 a well known fact that the Finnish and Swedish owners sold their ferries after 8-10 years in service to owners operating in entirely different areas of the world. Thus it would only be logical to build the ferries for worldwide trade.
German 'Group of Experts': This is the shipowners' concern. The yard builds the vessel according to the contractual agreements, class rules and requirements of the maritime administration.
Subsequently the development of the ferries built for AB Slite and AB Sally from 1969 to 1980 beginning with "APOLLO" and "DIANA" and ending with "VIKING SALLY" was explained, the discussion between Sjöfartsverket/Wahnes on basis of his logbook concerning "bow ramp = collision bulkhead" for "DIANA II" the attitude of the F.B.N. as to "VIKING SALLY", etc. were outlined. Further the "Copenhagen Convention" was handed over as well as this 'Group of Experts' report about "The description of the process of conversion from design to production of the locking devices" which can be found as part of Subchapter 2.4.6. This 'Group of Experts' explained also the background of the "partial collision door" clause in the "VIKING SALLY" specification ("EARL OF GRANVILLE" conversion) and the initial offer of the yard to install this partial collision door for DM 45.000,-- which was rejected by the owners. It would, however, have been possible at any time to have these doors installed for less than DM 100.000,-- in case the trading area would be changed to outside of "sheltered waters" as it occurred when the ferry's route was changed to Tallinn-Stockholm.
JAIC: Probably a yard has to argue differently than a Government commission, who will definitely and sharply draw attention to the faulty practice followed by the maritime administrations of the Nordic countries for decades by accepting the bow ramp as upper extension of the collision bulkhead on car/passenger ferries. The JAIC is of the considered opinion that according to SOLAS the maritime administra-tions may not grant exemptions in this respect, even not if the ferry trades regularly within 20 nm from the nearest land. Stenström said that it is a fact that in the Baltic about 70 ferries have been trading on which the bow ramp was the collision bulkhead. Of these 70 ferries 35 had the interlock between ramp and visor. The first vessel with such a construction was built in Finland. Meyer Werft is not responsible for it, Stenström said. It is considered a fact that the way "VIKING SALLY's" visor/bow ramp were built corresponded in those years absolutely to the state of the art and technique.

On 30 November Klaus Rahka from the Finnish JAIC phoned a member of this 'Group of Experts' and reported the following:

This attitude was also reflected in the next telephone conversation on 12 December when Börje Stenström stated the following: